Overview
(The actual product is subject to the customer's product)
Process flow
1 The equipment is placed on the double-speed conveyor, after the product flow
to the state.
2 The CCD is installed on the Z axis, and the scanning position is adjusted up
and down. By moving the XY axis, the range of the scanning cell flows to the lower station.
3 The lower manual NG/putting side plate station, OK products are released,
and NG products are pushed to the external buffer.
Configuration list
S/N | Item | Brand | Quantity | Unit |
1 | Position device | SHINHOP | 1 | Pcs |
2 | Moving axis device | SHINHOP | 4 | Pcs |
3 | Laser cleaning machine | SHINHOP | 1 | Pcs |
4 | Cabinet | SHINHOP | 1 | Pcs |
5 | Electrical device | Chint/ Schneider | 1 | Pcs |
6 | PLC | Inovance/Mitsubishi | 1 | Pcs |
7 | Touch screen | Weinview | 1 | Pcs |
8 | Computer display/Host | EVOC/Dell | 1 | Pcs |